Aug 28, 2026
Global Renewable News

The Pole Problem: Closing the Field Gap in Wildfire Mitigation Before the Next Season

by Davoud Zamani, Gridwap

Ask a utility asset manager to describe their wildfire mitigation program, and the answer arrives in a familiar order. Vegetation management is first, the largest line item and the one regulators ask about most. The second line item is the covered conductor and the third and fourth are fast-trip settings and public safety power shutoff protocols. Then, at the far end of the capital plan, undergrounding: the permanent fix, California’s three large investor-owned utilities price between $1.85 million and $6.07 million per mile.

Somewhere in that sequence, often as a footnote in the inspection budget, sits the wood pole.

Undergrounding works. It is also, by the numbers, a generational program. PG&E launched the country’s largest such effort in 2021, targeting 10,000 miles. It reached 1,000 completed miles in October 2025, and projects 1,600 by the end of 2026, an estimated 18% reduction in system wildfire risk. That is four years of the most aggressive undergrounding push any U.S. utility has attempted. It is also 16 of the goal.

This ordering is understandable. It is also increasingly hard to defend on risk terms, and regulators have begun saying so. In the 2021 Brewer Fire in Grass Valley, the CPUC’s Safety and Enforcement Division cited PG&E for six violations, among them that the utility found woodpecker damage exceeding its own replacement threshold on the ignition-point pole and patched a single hole instead of replacing the structure, then let a 12-month replacement work order lapse without completion or reassessment. The fire burned 5.5 acres of Tier 2 high fire-threat district. On a windier day, the same pole and the same deferred work order would have produced a different headline.

An estimated 160 to 180 million wood poles are in service across the United States, and a 2026 review of utility pole failure in Engineering Failure Analysis notes that roughly 80% of North American utility poles are wood. Much of that fleet is operating deep into, or past, the 35-to-50-year service life that treated wood is credited with. Their structural condition is not a maintenance detail. It is a measurable wildfire variable that belongs in the asset risk register alongside conductor type and vegetation clearance.

The pole is both a fire cause and a fire casualty

The prevailing mental model treats the pole as a fire victim: something a wildfire happens to, where the question is whether the structure survives flame contact and the countermeasure is fire resistance. That model is not wrong. It is half the picture, and the half that arrives second.

A pole fails in two ways, and they compound. The ignition mode is mechanical. Wind loads the pole, the pole breaks, the energized conductor falls into cured grass and ignition follows in seconds. This requires no fire beforehand, only that residual strength has fallen below the load the wind imposes. The propagation mode is thermal. Once a fire is burning, whether ignited here or arriving from elsewhere, flame contact consumes poles along the corridor, spreading the fire and turning one ignition into a multi-day rebuild across miles of line.

The modes share a root cause and a location. A pole with a decayed groundline is both more likely to break under wind and less able to survive flame contact, because the same lost cross-section that reduces bending capacity also reduces the material available to char before collapse. Decay does not choose one mode. It degrades both.

This matters for how utilities evaluate interventions. A treatment that restores capacity but burns addresses ignition and abandons the asset during propagation. A treatment that resists fire but does nothing for capacity fails in the other direction, since the pole never reaches flame contact, having already broken. The requirement applies to the same asset in the same zone.

Residual strength is the variable that decades of deterioration erode:

  • Groundline decay. The zone from six inches above grade to two feet below is where moisture, oxygen and soil organisms meet. Fungal decay hollows the pole from the inside out, often leaving an intact-looking shell over a compromised core. Bending stress peaks at groundline, making it the worst place to lose material. It is also where surface fuels concentrate and flame contact is most likely.
     
  • Woodpecker damage. Cavities remove material and open paths for water intrusion, accelerating decay, as Brewer illustrates.
     
  • Checking and splitting. Wet-dry cycling opens lengthwise checks that admit moisture, reduce shear capacity and give flame a path into the pole’s interior.
     
  • Load accumulation. A pole set decades ago to carry a primary conductor and a neutral now also carries telecom, fiber, transformers and reclosers. Every attachment adds weight and wind-catching area, so the load has grown while decay has quietly removed the wood resisting it. Demand rises, capacity falls and eventually they meet.
     

The picture from the engineering literature is consistent: a pole retaining a fraction of its original strength can stand for years without incident, then fail in the first wind event exceeding its degraded capacity. Standing is not the same as sound. That gap, between what an asset register records as “in service” and what the asset can withstand on a red flag day, is the field gap this article is about.

Why the inspection cycle is not enough

Inspection cycles are set by state rule or internal standard. California’s General Order 165 is representative: annual patrols in urban and high fire threat areas, detailed inspections of overhead equipment every five years and intrusive inspection of wood poles over 15 years old on a ten-year cycle, stretching to twenty once a pole has passed. Three structural problems limit what that delivers.

First, the interval is long relative to the hazard. A pole presumed sound for two decades accumulates attachments and decay throughout, and the annual patrol filling the gap is a visual check that cannot see groundline section loss at all. Decay is not linear; once a fungal colony is established and moisture retained, section loss accelerates.

Second, the queue is longer than the season. Brewer was not a detection failure. PG&E found the damage, wrote the work order, and did not complete it. Utility backlogs are structural: after a 2019 incident in which 26 poles failed, Seattle City Light committed to clearing roughly 6,000 poles needing replacement or reinforcement at 1,000 to 2,000 annually, constrained by crews, materials, and budget. Southern California Edison budgeted $1.1 billion over three years to inspect 1.4 million poles, targeting 35,000 replacements a year. Replacement runs at a few percent of the fleet annually, set by crew capacity rather than capital, and a wildfire-driven acceleration does not fit inside it.

Third, the assessment gives a condition grade, not a risk score. Knowing a pole has lost 30% of its groundline section is useful. Knowing whether that pole, at that span, in that fuel and wind regime, is a candidate for catastrophic ignition is a different question, requiring structural conditions to be layered against wildfire consequence modeling.

Prioritization: intersecting three data layers

The utilities making real progress are not treating pole hardening as a fleetwide program. They are treating it as a targeting problem, aimed at the intersection of three layers most organizations already own but rarely join: structural condition (inspection records, decay measurements, remaining strength, attachment load), usually the most complete layer and the most siloed; ignition consequence (fuel type and continuity, slope, fire perimeters, wind corridor modeling, downwind exposure), typically living in the wildfire mitigation group on another system and refresh cycle; and circuit criticality (whether the span stays energized in high wind, the protection scheme, whether de-energization is viable).

The intersection of all three should be far smaller than any one layer alone: poles simultaneously degraded, sited in high-consequence fuel and on circuits that stay energized in wind are a subset of a subset of a subset. Utilities that have not run this join often assume the hardening problem is fleet-wide, when the acute-risk population may be small enough to address in a single construction season. The fleetwide framing produces paralysis; the intersection framing produces a work plan. The CPUC has pointed the same way, observing that with climate-informed modeling down to individual poles, utilities can locate the most at-risk segments and decide which warrant undergrounding. The same logic applies to hardening, at a fraction of the cost.

Reinforcement as a capital strategy, not a stopgap

Once the target list is defined, the question is what to do with those poles. Replacement is the default answer and the wrong default for most of the list.

Reinforcement, the category of restoring or augmenting a degraded pole’s capacity in place, has existed in utility practice for decades, as steel trusses and stubs and remains in routine use: Ohio Edison’s inspection program explicitly reinforces rather than replaces some poles. What has changed is the range of approaches, the quality of validation data behind them and the recognition that reinforcement can be a permanent asset decision rather than a bridge to replacement.

The industry already has a precedent for this logic in covered conductor. The Public Advocates Office notes that, per project, it takes one to two years to install against three to four years for undergrounding, at roughly a third of the cost, letting a utility protect nearly four miles for the price of burying one. The CPUC has called aggressive covered conductor installation its preferred strategy on the grounds that it delivers ignition risk reduction comparable to undergrounding at lower cost.

Reinforcement offers the same trade at the structure level. It is typically a same-day, small-crew operation with no customer outage, so throughput per crew-day is a multiple of replacement throughput, at a fraction of the unit cost. Both ratios are site- and method-dependent and belong in a utility-specific business case rather than a rule of thumb. Two advantages matter disproportionately: many of the highest-risk poles sit on slopes, in backcountry right-of-way, at the wildland interface, exactly where replacement is most expensive and a small footprint counts most. And in-place work avoids excavation, pole disposal and easement renegotiation, shortening the permitting path.

Because the pole fails in two modes, any approach worth evaluating has to answer for both, plus the decay driving them.

On structural capacity: what is the restored bending capacity relative to the original design class, how is it measured, does it address the groundline zone where stress peaks and how does it compare against the wind loading the span sees with today’s attachments?

On fire performance: how does the treated pole behave under direct flame contact, against what test standard, does fire exposure degrade the structural claim and does the method protect the groundline zone where surface fuels gather?

On durability: does it exclude moisture and arrest decay, or encapsulate a decaying member and defer the problem? What is the reinforcement’s service life against the host pole’s remaining life? Is there third-party test data at recognized standards, from protocols resembling field conditions?

A method answering well in one group and poorly in another is not a partial solution. It is a solution to one failure mode and an open exposure on the other.

The documentation standard is rising, and it sets the accounting treatment

This is the part of the discussion that has changed most sharply in recent years. Regulators, and increasingly insurers and capital markets, are no longer satisfied with evidence of expenditure. They want evidence of outcome: risk reduction traceable to specific assets, supported by validation that did not originate with the vendor selling the solution. The organization needs to demonstrate, asset by asset, the pre-treatment condition, the intervention applied, the capacity restored, the test data behind the claim, and how that maps to a modeled reduction in ignition probability on that span.

There is a second reason that discipline matters, and for capital planners, it may be decisive. Under FERC’s Uniform System of Accounts, work extending an asset’s service life or capacity is capitalized to Account 364, Poles, Towers and Fixtures, entering rate base and depreciating over the asset’s useful life. Repair that does not extend life is expensed to Account 593, Maintenance of Overhead Lines and deducted in the year incurred. The dividing line is not the technique or the dollars spent. It is whether the work is planned, programmatic and life-extending.

That distinction has teeth. SCE’s Pole Loading and Deteriorated Pole programs are structured, systematically planned, capital-tracked efforts, treated accordingly through the CPUC’s rate case process. Brewer sits at the other end: a patch on a pole, internal standards said to replace, work order lapsed, no program wrapped around it. Reactive, non-life-extending, and when it went wrong, indefensible.

So, the same physical intervention lands on either side of the line depending on the program around it. Reinforcement performed ad hoc, as emergency response to a failed inspection, looks like maintenance. The same reinforcement against a prioritized target list, with documented pre- and post-treatment conditions, validated capacity restoration and a defined service-life extension, looks like a capital program. The engineering is identical. The regulatory treatment, and therefore the funding path, is not.

The targeting analysis and the documentation chain are not overhead on the real work. They are what make it fundable, and the same records will satisfy an insurer, a rating agency and eventually a litigator.

The window is the point

Here is the arithmetic that should sit at the center of every Q4 capital conversation. Undergrounding is the durable answer and, at the pace the leading program is achieving, a generational one. Full replacement is capacity-constrained in a way that no budget increase resolves quickly, because the binding constraint is crews and permits, not dollars. Vegetation management is necessary and does not address the structure. Every one is worth doing. None closes the exposure between now and the next wind event in cured fuel.

The pole fleet is the field gap: where a well-targeted, fast-deploying intervention can move the risk needle in a season rather than a decade, and where, designed as a program rather than a series of repairs, the spend can be capitalized rather than expensed.

None of this argues against undergrounding, against replacement where a pole is too far gone to reinforce, or against the vegetation program. It argues for sequencing. Harden the intersection set now. Replace on the normal cycle. Underground the corridors where the consequence math justifies it. Build the documentation chain from day one.

The pole has been the last asset in the wildfire conversation for a long time, because it is unglamorous and because the industry has treated it as infrastructure rather than a risk variable. The physics have never agreed with that ordering, and the regulatory environment is catching up. The remaining question is whether utilities move the pole up the priority list on their own analysis, or wait for an event to move it for them.

Davoud Zamani holds a Ph.D. in chemical engineering and material science from the University of Arizona, and has a background spanning engineering, business development and cross-functional leadership across multiple technology sectors. As co-founder and CEO of GridWrap, he guides the company’s strategic direction and its work with utilities to strengthen aging grid infrastructure.