December 4, 2024
Global Renewable News

CORPOWER
CorPower Ocean and Maersk Supply Service install subsea cable for HiWave-5 Project

October 6, 2022

CorPower Ocean and Maersk Supply Service have successfully installed a 6.2km subsea export cable off the coast of northern Portugal to energise the flagship HiWave-5 Project.

The 100-tonne cable was installed using the Maersk Achiever vessel and will provide power and data connection from an on-land substation in Aguçadoura to the wave energy demonstration site 5.5km offshore.

Now connected to the national grid of Portugal, the site will initially accommodate the recently unveiled CorPower C4 Wave Energy Converter (WEC) which later form part of a larger four-system array, and one of the world's first grid-connected wave farms.  

CorPower Ocean Marine Operations Manager Robert Argo said the cable lay process marks another significant milestone for the HiWave-5 Project, which aims to introduce certified and warrantied WEC products to the market.

"We started the installation process by positioning the Maersk Achiever in a safe water depth within the cable corridor, approximately one kilometre offshore," said Mr Argo. "A messenger line was passed from an onshore winch to the Maersk Achiever, and then connected to a cable pull-in head. As the cable was being deployed buoyancy was attached to assist with the cable float into shore. Once onshore the cable was pulled through a pre-installed cable conduit running under the beach and into the on-land substation, while the remaining cable was deployed using an onboard cable tensioner.

 "During the lay operation, cable protection was added to provide additional mass where required for on-bottom stability. Various parameters were also monitored throughout including cable tension, cable departure angle and touch down monitoring. On completion a visual and positioning survey was carried out by a remotely operated vehicle.  

"The cable lay process is a notoriously challenging aspect for marine energy projects, with much planning required and adaption to weather windows and ocean conditions. We are thankful to our highly diligent and professional partners, including Maersk Supply Service for their close support throughout the operation entire."

CorPower is now gearing up for the arrival of the C4 PTO (Power Take Off) system, which has completed a rigorous one-year dry test programme in Sweden. Once transported the PTO will be integrated with a composite hull, which was custom built at CorPower Ocean's Portuguese base, in Viana do Castelo - home to its innovative Composite Hull Development Programme.

 Having successfully completed tests to verify power conductors and fibre communication cores, the CorPower C4 WEC will later be fused to the cable through a quick-connect interface located at the anchor-head. While providing power connection to feed electricity to shore through the 7.2kV cable it will also deliver high speed communication to the wave farm through fibre optic cores.

A Press Kit with background information and high-resolution images can be found >>here. For further information on CorPower Ocean visit www.corpowerocean.com or email ida.malmborg@corpoweroocean.com  

CorPower Ocean
CorPower Ocean brings high-efficiency Wave Energy technology enabling reliable and cost-effective harvesting of electricity from ocean waves. With our research and development spanning decades, our innovations are inspired by the pumping principle of the human heart. Ocean energy brings stability to the clean energy mix, accelerating the transition to zero-carbon energy. Headquartered in Sweden, with offices in Portugal, Norway and Scotland, we design, build and install turnkey solutions that allow our customers to power the planet with clean energy from ocean waves.

For more information

CorPower Ocean

www.corpowerocean.com


From the same organization :
10 Press releases