Nova Scotia Power is undertaking site cleanup and removal of the Grand Etang wind turbine, which is expected to be completed within the next two weeks.
The turbine has not been in operation since early January following an unexpected collapse of the turbine structure. No one was onsite at the time of the incident and there we no injuries.
A detailed investigation into the turbine collapse has been underway over the past few months, with further analysis of the data and equipment required before the cause of the incident can be confirmed.
Crews have been on-site cleaning up debris from the property and mobilizing a crane that will lift the wind turbine and tower components onto flatbeds for transport. It's expected that site cleanup and removal of the turbine will be completed within the next two weeks.
Constructed in 2002, Grand Etang was one of the first wind installations in Nova Scotia, with a single 660 kilowatt Vestas V47 wind turbine. That particular turbine model is not used at any other site in the province, either by Nova Scotia Power or independent wind producers.
Nova Scotia Power purchases electricity produced from over 300 public and privately-owned wind turbines in operation across the province.