Van Oord has been awarded the contract by Ørsted for the cable installation works at the Greater Changhua 1 & 2a offshore wind farms. The wind farms are located between 35 and 60 kilometres off the west coast of Changhua County, Taiwan. Greater Changhua 1 & 2a offshore wind farms will supply sustainable energy to approximately 1 million households per year.
Van Oord is responsible for the transportation, installation and burial of the 111 inter array cables, with a total length of approximately 135 kilometres, and the 3 export cables, with a total of approximately 145 kilometres. To carry out the work, Van Oord will deploy its dedicated cable-laying vessel Nexus, equipped with a cable carousel with a capacity of 5,000 tonnes. Van Oord's own trencher Dig-It will bury the cables to the required depth. The installation work starts in 2021.